Hyperion Data Center

32°28′38″N 91°37′56″W / 32.477149°N 91.632333°W / 32.477149; -91.632333

Hyperion Data Center
Image posted by Zuckerberg showing the construction plan for Hyperion superimposed on Manhattan
Alternative names
  • Richland Parish Data Center
  • Project Sucre
  • Project Laidley flagship site
  • Franklin Farms megasite
General information
StatusUnder construction
LocationHolly Ridge, Louisiana, United States
Elevation0.03 km
Year built2024–2032
Cost> US$50 billion
OwnerMeta Platforms
Technical details
Floor area4,000,000 sq ft (371,612 m2)
Website
datacenters.atmeta.com/richland-parish-data-center/

The Richland Parish Data Center, nicknamed "Hyperion", is a planned artificial intelligence data center by Meta Platforms under-construction along Louisiana Highway 183 in Richland Parish, Louisiana, just outside of Holly Ridge. It is one of a number of "titan clusters" being built in preparation for the emergence of AI superintelligence. Modern technological researchers disagree as to whether or not superintelligence will ever exist, though Meta CEO Mark Zuckerberg has expressed belief that its creation is inevitable. Initial financing plans provided for at least $27 billion of investment. In July 2026, Meta announced the campus would expand to 5 gigawatts of compute capacity, nearly doubling the land area noted in the image posted by Zuckerberg showing the construction plan for Hyperion, raising planned investment to more than US$50 billion, with roughly 2 GW expected online by 2030 and full build-out around 2032.

History

Meta was considering potential locations for their flagship data center in early 2024. Before being announced later in December, the plan was completely secret; meetings held between involved organizations and even government officials could only refer to it by the codename "Project Sucre" to protect it from potential corporate espionage. The data center was first announced on December 4, 2024, though its full scale was yet to be revealed. At first, Meta would not even claim responsibility for it, channelling all of its investments through the secret shell subsidiary Laidley LLC.

We set out looking for a place where we could expand into gigawatts pretty quickly, and really get moving within that community on a large plot of land very quickly. We looked at finding very, very large contiguous plots of land that had access to the infrastructure that we need, the energy that we needed, and could move very, very quickly for us.

— Rachel Peterson, Meta Vice President of Data Centers

The Louisiana-based Entergy Corporation, aiming for the facility to be built in its own backyard, negotiated a deal with the government of Louisiana to provide Meta with enormous tax breaks if they agreed to build Hyperion there. The Louisiana legislature responded by passing Act 730, which provides significant tax rebates on the purchase or lease of equipment for building and operating data centers. Meta found the arrangement acceptable, and bought a plot of land from the government. The government also had to further amend its laws to allow Meta to do this, as pre-existing policy forbade purchasing land directly from the government instead of hosting a public auction. The plot of land, originally called Franklin Farms, was purchased from the Franklin family in 2006 by the government, intending for it to be developed into an automotive manufacturing plant.

Greater attention was brought to Hyperion when Zuckerberg posted about the project on July 14, 2025, on Threads. The project subsequently caught media attention for its large size, as Zuckerberg's post portrayed the structure superimposed over Manhattan (pictured). The construction site spans 2,250 acres (9.1 km2), with a total planned floor area of 4,000,000 square feet (371612 m2) across the campus.

Meta initially reported the construction cost to be over $10 billion, but in October 2025, it announced a partnership with Blue Owl Capital providing for at least $27 billion. In July 2026, Meta announced a further expansion of the project, lifting its total planned investment above $50 billion. A Wall Street Journal investigation showed that although Meta is behind the project, it is owned through Beignet Investors, a special purpose vehicle managed by Blue Owl structured as an 80:20 joint venture where Meta is the minority partner and tenant so that the project is off-balance sheet. The construction is financed through a bond sale; lease payments will provide the cash flows to repay to bondholders. The initial four-year Hyperion lease is irrevocable and starts in 2029, renewable for up to 20 years, with bonds backed by a guarantee for the entire two decades. The company's aggregate initial lease commitment is about $12.3 billion.

Operation

The facility is expected to consume up to 5 gigawatts (GW) of computational power, a figure Meta confirmed in July 2026 with roughly 2 GW expected online by 2030 and the full campus completed around 2032. As part of their deal made with Meta, Entergy plans to be able to produce at least 3.8 GW of electricity for the operation.

Response to the project

Louisiana Governor Jeff Landry thanked Meta for their decision to build Hyperion in Louisiana, stating that it would "create opportunities for Louisiana workers to fill high-paying jobs of the future." and calling it "A New Chapter" for the state. The Louisiana Economic Development (LED) state agency further praised the project, citing Meta's estimate that it would create 1,500 jobs. Additionally, Richland Parish Supervisor Joey Evans stated that he was excited about the project.

As part of their agreement with Meta, Entergy announced their plan to increase electricity production state-wide. They say that this will result in the cost of energy reducing, though Entergy filings revealed in June 2025 that the cost of electricity would rise and be passed onto consumers. Meta also pledged to match all of Hyperion's power consumption with 100% environmentally friendly electricity production. So far, Entergy has begun building three gas-powered combined-cycle power plants and a substation in response to the project.

Delta Community College announced in response to Hyperion's construction that it would expand its construction and trade programs.

In January 2025, Business Facilities Magazine selected Hyperion for its annual Deal of the Year Platinum Award for 2024.

Much of the initial backlash following Hyperion's announcement centered around the fast-tracked approval of the project by the state government, and skepticism around Meta's various claims (environmental friendliness, 100% renewable energy, local economic stimulation, price reductions). The Sierra Club criticized Meta for gentrifying the surrounding area, and was highly skeptical of their promise to keep it environmentally friendly. Environmental activist group Earthjustice attempted to have a subpoena of Meta approved to determine if they were compliant with environmental protection laws, though they were unsuccessful.

Many residents of Holly Ridge have been critical of the construction, complaining about the increased construction vehicle traffic and intense gentrification. Another point of contention is Meta's continued reliance on out-of-state contractors in the facility's construction in spite of their previous commitment to "hire as many local folk as [we] possibly can." In spite of Entergy's continual denial that the facility's construction could adversely affect the power grid, numerous electrical outages have been reported since construction began.

See also

Notes

  1. ↑ the Smalling Substation, paid for by Meta

References

  1. ↑ "Meta to spend hundreds of billions on AI data centres, says Mark Zuckerberg". BBC News. July 15, 2025. Retrieved January 23, 2026.
  2. ↑ Brook, Jack; Sainz, Adrian (December 4, 2024). "Meta to build $10 billion AI data center in Louisiana as Elon Musk expands his Tennessee AI facility". AP News. Retrieved May 27, 2026.
  3. ↑ Zuckerberg, Mark (July 30, 2025). "Personal Superintelligence". Meta.com. Archived from the original on May 24, 2026. Retrieved May 29, 2026.
  4. ↑ Capps, Kriston (August 24, 2025). "Why Meta's Hyperion Data Center Looks Like It's Crushing New York City". CityLabs Design Edition. Bloomberg L.P. Archived from the original on October 11, 2025. Retrieved May 29, 2026.
  5. 1 2 "Meta Announces Joint Venture with Funds Managed by Blue Owl Capital to Develop Hyperion Data Center". Meta Investor Relations. November 21, 2025. Retrieved May 26, 2026.
  6. 1 2 "Meta's Louisiana data center investment to reach $50 billion, aided by generous tax incentives". CNBC. July 13, 2026. Retrieved July 15, 2026.
  7. ↑ Keegan, Jon (December 15, 2025). "The power play behind Hyperion, Mark Zuckerberg's colossal data center being built in rural Louisiana". Sherwood News. Retrieved May 28, 2026.
  8. ↑ "LAIDLEY LLC". OpenCorporates. Retrieved May 27, 2026.{{cite web}}: CS1 maint: url-status (link)
  9. ↑ Cohn, Scott (June 25, 2025). "To land Meta's massive $10 billion data center, Louisiana pulled out all the stops. Will it be worth it?". CNBC. Retrieved January 23, 2026.
  10. ↑ "Louisiana Laws – Louisiana State Legislature". legis.la.gov.
  11. ↑ Riegel, Stephanie (January 25, 2025). "The behind-the-scenes story of how Meta's $10 billion data center came to Louisiana". The Times-Picayune New Orleans Advocate. Retrieved May 26, 2026.
  12. ↑ Lincoln, Sue (July 18, 2017). "Whatever Happened To...The Northeast Louisiana Industrial Megasite?". WRKF. Retrieved May 27, 2026.
  13. ↑ Zuckerberg, Mark (July 14, 2025). "We're also building Hyperion, which will be able to scale up to 5GW". Threads. Archived from the original on February 3, 2026. Retrieved February 3, 2026.
  14. ↑ Keegan, Jon (January 24, 2025). "Zuckerberg: Meta building city-sized AI data center, going on $65 billion spending spree". Sherwood News. Retrieved May 28, 2026.
  15. ↑ Abugov, Josie (November 20, 2024). "Tech giant's plan for huge Louisiana facility clears initial hurdle. Concerns raised over power needs". The Times-Picayune New Orleans Advocate. Retrieved May 27, 2026.
  16. ↑ "Meta's Richland Parish Data Center" (PDF). Meta Data Centers. Archived (PDF) from the original on January 29, 2026. Retrieved February 3, 2026.
  17. 1 2 Rudegeair, Peter; Santilli, Peter (August 17, 2026). "Why Big Tech's AI Spending Is $3 Trillion Higher Than It Seems". The Wall Street Journal.
  18. ↑ "Meta says Louisiana data center cost will exceed $50 billion". United Press International. July 13, 2026. Retrieved July 15, 2026.
  19. ↑ Zeff, Maxwell (July 14, 2025). "Mark Zuckerberg says Meta is building a 5GW AI data center". TechCrunch. Retrieved January 23, 2026.
  20. ↑ Swaine, Liz (December 4, 2024). "Meta AI facility will be 'game changer' for Louisiana as Jeff Landry announces $10B plan". The Shreveport-Bossier City Advocate. Retrieved May 27, 2026.
  21. ↑ Landry, Jeff (October 22, 2024). "Louisiana Governor Jeff Landry: Louisiana needs tax reform to avoid a $1.5 billion shortfall and more". The Times-Picayune New Orleans Advocate. Retrieved May 27, 2026.
  22. ↑ "Meta Selects Northeast Louisiana as Site of $10 Billion Artificial Intelligence Optimized Data Center; Governor Jeff Landry Calls Investment 'A New Chapter' for State – LED | Louisiana Economic Development". www.opportunitylouisiana.gov. December 4, 2024. Retrieved January 23, 2026.
  23. ↑ "Entergy Louisiana to power Meta's data center in Richland Parish". Entergy. December 6, 2024. Retrieved May 26, 2026.
  24. ↑ "Meta selects Entergy, Northeast Louisiana as site of $10B data center". Entergy. December 5, 2024. Retrieved May 26, 2026.
  25. ↑ McKendry, Nolan (June 10, 2025). "Ratepayers on the hook for $470M in data center infrastructure". The Center Square Louisiana. Franklin News Foundation. Retrieved May 28, 2026.
  26. ↑ "Entergy announces $5B in customer savings delivered by data center agreements; issues "Fair Share Plus" pledge". Entergy. March 5, 2026. Retrieved May 26, 2026.
  27. ↑ "Data center boom will ultimately drive down electricity costs". Entergy. December 18, 2025. Retrieved May 26, 2026.
  28. ↑ "Entergy Louisiana receives LPSC approval for major infrastructure investments to support Meta's data center and improve reliability". Entergy. August 20, 2025. Retrieved May 26, 2026.
  29. ↑ May, Phillip (August 27, 2025). "Meta's move to Louisiana: Good for the state, and a big win for Entergy customers". Entergy. Retrieved May 26, 2026.
  30. ↑ "Entergy Louisiana breaks ground on key substation to power data center in Richland Parish". Entergy. June 30, 2025. Retrieved May 26, 2026.
  31. ↑ James, Phoebe (November 4, 2025). "Entergy Louisiana and Energy Transfer sign agreement that supports reliable, affordable energy and economic growth in North Louisiana". Entergy. Retrieved May 26, 2026.
  32. ↑ "Louisiana Delta Community College Launches Data Technician Center Training Program". ladelta.edu. Retrieved May 26, 2026.
  33. ↑ "2024 Deals Of The Year & Impact Awards". Business Facilities Magazine. January 27, 2025. Retrieved May 26, 2026.
  34. ↑ Swaine, Liz (January 14, 2025). "Louisiana tops in the nation with big win on Meta AI center". The Shreveport-Bossier City Advocate. Retrieved May 26, 2026.
  35. ↑ Remrey, Madison (January 8, 2025). "Meta's investment in Richland Parish earns Louisiana Business Facilities' highest honor". KNOE News 8. Retrieved May 26, 2026.
  36. ↑ Abraham, Roshan. "Louisiana Hands Meta a Tax Break and Power for Its Biggest Data Center". Wired. ISSN 1059-1028. Retrieved May 26, 2026.
  37. ↑ Guilbeau, Julia; Abugov, Josie (November 22, 2024). "What are AI data centers? Here's how the planned Meta facility in Louisiana could work". The Times-Picayune New Orleans Advocate. Retrieved May 27, 2026.
  38. ↑ Muller, Wesley (August 20, 2025). "Entergy Louisiana gains regulatory approval for massive Meta power project • Louisiana Illuminator". Louisiana Illuminator. Retrieved May 28, 2026.
  39. ↑ Anderson, Reese (October 30, 2025). "In Rural Louisiana, Meta's New Data Center Promises Growth—But at What Cost?". Sierra. Sierra Club Delta. Retrieved May 26, 2026.
  40. ↑ Abugov, Josie (November 19, 2024). Riegel, Stephanie (ed.). "Meta, Facebook's parent company, plans to build multi-billion dollar AI data center in Louisiana". The Times-Picayune New Orleans Advocate. Retrieved May 27, 2026.
  41. ↑ Miller, Susan Stevens (July 2, 2025). "Re: Application for Approval of Generation and Transmission Resources in Connection with Service to a Single Customer for a Project in North Louisiana, Docket No. U-37425". Counsel for the Alliance for Affordable Energy and Union of Concerned Scientists. Retrieved May 26, 2026 – via Lpscpubvalence.lpsc.louisiana.gov.
  42. ↑ Goldman, Sharon (March 26, 2026). "Meta's $27 billion AI data center is causing chaos in small town Louisiana". Fortune. Retrieved May 26, 2026.
  43. ↑ Hawkins, Drew (November 19, 2025). "Construction on Meta's largest data center brings 600% crash spike, chaos to rural Louisiana". Gulf States Newsroom. WWNO. Retrieved May 29, 2026.