The JAMALI (short for Java–Madura–Bali) is a synchronous grid or interconnection that serve three islands (Java, Madura, and Bali) with almost 160 million peoples in Indonesia. The JAMALI covers three islands (Java, Madura, and Bali) in Indonesia. It covers several provinces, those are Jakarta, Banten, West Java, Central Java, Yogyakarta, East Java, and Bali. The JAMALI was established in the early 1980s.
The JAMALI is supplied by coal thermal power plants (60,2%), gas thermal power plants (30,5%), renewable power plants (8,4%), and others (0,9%). The JAMALI covers about 79% Indonesian power generation.
Distribution
The JAMALI supplies 6 distribution units of Perusahaan Listrik Negara across Java, Madura, and Bali. This contributes to 60% of Indonesian electricity load.
The 1997 Java–Bali blackout was a power outage across Java and Bali on April 13, 1997 10.15–13.15 UTC+7 and 17–20 UTC+7 due to trip on 500 kV Suralaya which equals to 1250 MW (25% of generation supply).
The 2009 Bali blackout was a power outage that occurred across much of Bali on September 16, 2009 due to failure on 200 MW undersea cable from Java.
2015 Bali blackout
The 2015 Bali blackout was a power outage that occurred across much of Bali from February 21 – March 1, 2015 due to scheduled maintenance of Gilimanuk gas thermal power plant.
2018 Java blackout
The 2018 Java blackout was a power outage that occurred across much of Java from September 5 – due to failure on 500 kV transmission Paiton–Grati, Paiton–Kediri and Kediri–Pedan.
2019 Java blackout
The 2019 Java blackout was a power outage that occurred across much of Java from August 4, 2019, 11:50 (UTC+7) to August 5, 2019, at 22:00 (UTC+7) (depending on area) because of a disturbance on the transmission side of Ungaran–Pemalang 500 kV which resulted in energy transfers from east to west failing. This caused half of the Java into blackout.
2025 Bali blackout
The 2025 Bali blackout was a power outage that occurred across Bali from May 3, 2025 04:00 pm (UTC+7) to May 5, 2025 03:30 pm (UTC+8) due to Unit 2 Celukan Bawang coal thermal power plant maintenance and failure on undersea cable from Java.
2026 Java blackout
The 2026 Java blackout was a rolling power outage that occurred across Java from June 8 to June 19, 2026 (UTC+7). The grid had several power outages due to insufficient supply of coals for coal thermal power plants in Java.