Construction started
21 October 2014
Completed
July 2024
Height
Roof229.8 m (754 ft) 193 m (633 ft) 175 m (574 ft)
Technical details
Floor count54, 68, and 60
Design and construction
ArchitectsHandel Architects
Hollwich Kushner
DeveloperKushner Real Estate Group
Website
www.journalsquared.com

Journal Squared, or J2, is a three-tower retail and residential complex at Journal Square in Jersey City, New Jersey.

Site

The site of the project is adjacent to the Journal Square Transportation Center on Summit Avenue across from the Hudson County Administration Building, the county seat of Hudson County and the Newkirk House, the oldest extant building in the county.

Funding and abatements

Journal Squared was developed by Kushner Real Estate Group. It was first approved by the city council in December 2012 and was later granted a 30-year tax abatement and $10 million in bonds.

Design

The project was designed by Handel Architects and Hollwich Kushner. The project consists of three towers, in which 2,000 new office, residential, and retail units would be built, with the residential spaces making up the majority of the complex. It also includes a large plaza that occupies a portion of the lot, which can be used for public gatherings and functions as an open space in the complex.

Construction

The project broke ground in October 2014 with the first building topping out in December 2015 at 54 stories and 574 ft (175 m). Construction began on the second and tallest of the three towers in 2018. Elicc Americas Corp. was the facade manufacturer and installer The second tower topped out in December 2019. The third tower, consisting of 600 units and rising 60 stories, broke ground in October 2021. The buildout of all three phases were completed in July 2024. With this, the towers joined among the tallest buildings in the city. In November 2024, there was a ribbon-cutting ceremony for the third tower.