National Highways Development Project

The National Highways Development Project (NHDP) was a project of four laning of existing national highways and six laning of selected major national highways of India. The project was started in 1998 under the leadership of Prime Minister, Atal Bihari Vajpayee. National Highways account for only about 2% of the total length of roads, but carry about 40% of the total traffic across the length and breadth of the country. This project is managed by the National Highways Authority of India (NHAI) under the Ministry of Road, Transport and Highways. The NHDP represents 49,260 km of roads and highways work and construction in order to boost economic development of the country. The government has planned to end the NHDP program in early 2018 and subsume the ongoing projects under a larger Bharatmala project.

The Network of National Highways in India

Project phases

The project is composed of the following phases:

National Highways Development Project at a glance
NHDP PhaseParticularsLengthIndicative cost ₹ ( in cr)
NHDP-I & IIBalance work of GQ and EW-NS corridors13,000 km (8,100 mi)42,000
NHDP-III4-laning10,000 km (6,200 mi)55,000
NHDP-IV2-laning20,000 km (12,000 mi)25,000
NHDP-V6-laning of selected stretches5,000 km (3,100 mi)17,500
NHDP-VIDevelopment of expressways1,000 km (620 mi)15,000
NHDP-VIIRing Roads, Bypasses, Grade Separators, Service Roads etc.700 km (430 mi)15,000
Total45,000 km (28,000 mi)1,690,500 (Revised to 2,200,000)

Note: 1 crore= 10 million

Timeline of the National Highways Development Project
PriorityNHDP PhaseLength (km)StatusApprovalCompletion Target
1 Phase I5,846 km (3,633 mi)CompleteDecember 2000December 2006
2 Phase II7,300 km (4,500 mi)CompleteDecember 2003December 2009
3 Phase III A4,000 km (2,500 mi)Largely completedMarch 2005December 2009
4 Phase V6,500 km (4,000 mi)Largely completedNovember 2005December 2012
5 Phase III B6,000 km (3,700 mi)Largely completedMarch 2006December 2012
6 Phase VII A700 km (430 mi)Partially completed / transferredDecember 2006December 2012
7 Phase IV A5,000 km (3,100 mi)Transferred to Bharatmala or later programmesDecember 2006December 2012
8 Phase VII BTransferred / not implemented as NHDPDecember 2007December 2013
9 Phase IV B5,000 km (3,100 mi)Transferred to Bharatmala or later programmesDecember 2007December 2013
10 Phase VI A400 km (250 mi)Completed or transferredDecember 2007December 2014
11 Phase VII CTransferred / not implemented as NHDPDecember 2008December 2014
12 Phase IV C5,000 km (3,100 mi)Transferred to Bharatmala or later programmesDecember 2008December 2014
13 Phase VI B600 km (370 mi)Transferred / supersededDecember 2008December 2015
14 Phase IV D5,000 km (3,100 mi)Transferred to Bharatmala or later programmesDecember 2009December 2015

"Financing of the National Highway Development Programme" (PDF). Archived from the original (PDF) on 28 February 2007.

Status from NHAI website

National Highways Development Project is being implemented in all phases. The present phases are improving more than 49,260 km of arterial routes of NH network to international standards. The project-wise details of NHDP all phases is below as of 18 May 2021:

NATIONAL HIGHWAY DEVELOPMENT PROJECT(NHDP)
Projects Total Length(Km.) Already 4/6 Laned(Km.) Under Implementation (Km.) Contracts Under Implementation (No.) Balance length for award(Km.)
NHDP GQ 5,846 5,846

(100.00%)

0 0 -
NS - EW

Ph. I & II

7,142 6,568 300 28 274
Port

Connectivity

435 383 52 7 -
NHDP Phase III 11,809 7,621 2,161 71 2,027
NHDP Phase IV 13,203 4,058 6,050 105 3,095
NHDP Phase V 6,500 2,564 1,428 33 2,508
NHDP Phase VI 1,000 - 184 9 816
NHDP Phase VII 700 22 94 4 584
NHDP Total 46,635 27,062 10,269 257 9,304
Others (Ph.-I, Ph.-II & Misc.) 2,048 1,743 305 18 -
SARDP -NE 110 110 0 1 -
Total by NHAI 48,589 28,915* 10,574 276 9,304
*Total 20,000 km was approved under NHDP Phase IV, out of which 13,203 km was assigned to NHAI and remaining Km with MoRTH.

Subsummation in Bharatmala project

National Highway Development Project will close by first half of 2018, with the launch of Bharatmala project. 10,000 km of highway construction left under NHDP will be merged with Phase I of the Bharatmala. Following the launch of Bharatmala Pariyojana in 2017, the remaining works under the NHDP were subsumed into Bharatmala Phase I. Concurrently, the government of India launched complementary infrastructure programmes such as Sagarmala for port led development and Setu Bharatam for the construction of road over bridges and under passes on National Highways.

See also

Similar rail development
Similar roads development
Similar ports and river transport development
Similar air transport development
Highways in India
General

References

  1. ↑ "Govt declares Golden Quadrilateral complete". The Indian Express. 7 January 2012.
  2. ↑ "National Highways Development Project Map". National Highways Institute of India. Archived from the original on 4 March 2016. Retrieved 19 February 2009.
  3. ↑ "Archived copy". Archived from the original on 1 January 2018. Retrieved 12 November 2016.{{cite web}}: CS1 maint: archived copy as title (link)
  4. ↑ "Archived copy". Archived from the original on 4 August 2009. Retrieved 12 November 2016.{{cite web}}: CS1 maint: archived copy as title (link)
  5. 1 2 3 4 5 6 7 "Annual report 2024-2025" (PDF). 2025.
  6. ↑ "National Highways Authority of India, Ministry of Road Transport & Highways, Government of India". nhai.gov.in. Retrieved 18 May 2021.
  7. 1 2 Sood, Jyotika (18 April 2017). "NDA to kick off India's most ambitious roads programme ever". livemint.com/. Retrieved 25 June 2017.
  8. ↑ "Report of the Comptroller and Auditor General of India on Implementation of Phase-I of Bharatmala Pariyojana" (PDF). 2023.