| Qinshan Nuclear Power Plant | |
|---|---|
Qinshan Phase III Units 1 & 2 | |
![]() | |
| Country | China |
| Location | Qinshan, Zhejiang |
| Coordinates | 30°25′59″N 120°57′0″E / 30.43306°N 120.95000°E |
| Status | Operational |
| Construction began | March 20, 1985 (I) June 2, 1996 (II-1) April 1, 1997 (II-2) April 28, 2006 (II-3) January 28, 2007 (II-4) June 8, 1998 (III-1) September 25, 1998 (III-2) |
| Commission date | April 1, 1994 (I) April 15, 2002 (II-1) May 3, 2004 (II-2) October 5, 2010 (II-3) December 30, 2011 (II-4) December 31, 2002 (III-1) July 24, 2003 (III-2) |
| Owners |
|
| Operators |
|
| Nuclear power station | |
| Reactor type | PWR (I; II 1–4) CANDU PHWR (III 1–2) |
| Reactor supplier | China National Nuclear Corporation (I; II 1–4) Atomic Energy of Canada Limited (III 1–2) |
| Cooling source | Hangzhou Bay |
| Thermal capacity | 1 × 966 MWth 4 × 1930 MWth 2 × 2064 MWth |
| Power generation | |
| Units operational | 1 × 308 MW 2 × 610 MW 2 × 619 MW 2 × 677 MW |
| Make and model | 1 × CNP-300 (I) 4 × CNP-600 (II 1–4) 2 × CANDU 6 (III 1–2) |
| Nameplate capacity | 4110 MW |
| Capacity factor | 90.59% (2017) 88.21% (lifetime) |
| Annual net output | 32,614 GWh (2017) |
| External links | |
| Commons | Related media on Commons |
The Qinshan Nuclear Power Plant (秦山核电站) is a multi-unit nuclear power plant in Qinshan Town, Haiyan County, in Jiaxing, Zhejiang province, China.
It is the first nuclear power plant in mainland China, with a total capacity of 6.546 million kWh.
The construction of the units involved three separate phases.

Although Fangjiashan Nuclear Power Plant is technically a separate entity from Qinshan, the World Nuclear Association considers it to essentially be an extension of the Qinshan plant due to their proximity and the fact that the original two reactors built at Fangjiashan were initially intended to be built at Qinshan phase IV (which is no longer planned).
| Unit | Type | Model | Net power (MWe) | Gross power (MWe) | Thermal power (MWt) | Start construction | First criticality | Grid connection | Commercial operation | Notes |
|---|---|---|---|---|---|---|---|---|---|---|
| Phase I | ||||||||||
| Qinshan I | PWR | CNP-300 | 328 (308) |
350 (330) |
966 | 1985-3-20 | 1991-10-31 | 1991-12-15 | 1994-4-1 | |
| Phase II | ||||||||||
| Qinshan II-1 | PWR | CNP-600 | 610 | 650 | 1930 | 1996-6-2 | 2001-11-15 | 2002-2-6 | 2002-4-15 | |
| Qinshan II-2 | PWR | CNP-600 | 668 (610) |
708 (650) |
1930 | 1997-4-1 | 2004-2-25 | 2004-3-11 | 2004-4-3 | |
| Qinshan II-3 | PWR | CNP-600 | 619 | 660 | 1930 | 2006-4-28 | 2010-7-13 | 2010-8-1 | 2010-10-5 | |
| Qinshan II-4 | PWR | CNP-600 | 619 | 660 | 1930 | 2007-1-28 | 2011-11-17 | 2011-12-25 | 2011-12-30 | |
| Phase III | ||||||||||
| Qinshan III-1 | PHWR | CANDU 6 | 677 | 728 | 2064 | 1998-6-8 | 2002-9-21 | 2002-11-19 | 2002-12-31 | |
| Qinshan III-2 | PHWR | CANDU 6 | 677 | 728 | 2064 | 1998-9-25 | 2003-1-18 | 2003-6-12 | 2003-7-24 | |
In 2019 Qinshan 1 was upgraded and uprated to 350 MWe (net) from its original output power of 300 MWe.
In March 2025, Qinshan II-2 was upgraded to 708MWe (gross) from 650MWe after 20 year's maintanace.