The Edison (skyscraper)

The Edison
Daytime photograph of an unfinished tower foundation, with exposed rebar, concrete pillars, and loose gravel, seen through a chain link fence. Trees and the Milwaukee School of Engineering's (MSOE) Grohmann tower can be seen in the background.
Unfinished foundation of the Edison, as seen in September 2026
General information
StatusOn hold
Location1005 North Edison Street, Milwaukee, Wisconsin
Coordinates43°02′37″N 87°54′45″W / 43.0436569734289°N 87.91254953947164°W / 43.0436569734289; -87.91254953947164
GroundbreakingJune, 2025
Height
Height362 feet (110 m)
Technical details
Floor count31
Design and construction
ArchitectThronton Tomasetti
DeveloperNeutral
Main contractorC.D. Smith
Other information
Parking288

The Edison is a planned 31-story high-rise tower in Milwaukee, Wisconsin, US. Developed by Madison-based developer Neutral, the tower is planned to stand at a height of 362 feet (110 m), containing 378 luxury apartment units upon completion and will become the new tallest mass timber building in the world and surpassing the current record holder, the Ascent MKE. Construction of the tower first began in June 2025.

In September 2025, construction was halted due to significant cost issues and failure to pay the Fond du Lac–based general contractor C.D. Smith Construction, cited by Neutral as a result of the Trump administration's tarrifs, with Milwaukee County Circuit Court Judge Glen Yamahiro defaulting the property on June 29, 2026.

History

The Edison was originally proposed in 2021 by Madison-based developer Neutral as a 15-story, 220-unit building to be erected along Milwaukee's riverfront, with plans involving the demolition of the Rojahn & Malaney Co. floral warehouse located on the site. In January 2025, the company secured $133 million in additional financing from Arkansas-based Bank OZK and Chicago-based Pearlmark Real Estate for the project, with the projected cost at $203 million.

Neutral hired Chicago-based engineer firm Forefront Structural Engineers, New York–based architectural firm Thornton Tomasetti for the structure's façade and C.D. Smith Construction as the project contractor; the latter had previously worked on the current tallest mass timber tower, the Ascent MKE. The ground breaking ceremony was held in June 2025, with construction planned to be completed in 2027.

In September of 2025, construction on the tower was paused by contractor C.D. Smith Construction, with developer Neutral failing to pay $11.3 million out of the estimated $13.67 million of work that had been performed. Neutral cited the Trump administration's tariffs placed on imported and exported goods as the cause of the failure to pay, with the construction cost increasing to $230 million and the company unable to cover the additional costs. C.D. Smith file a lawsuit against Neutral in March 2025, alleging Neutral's failure to finance the work performed; Neutral failed to appear in court nor file a legally valid response by Wisconsin's statutory deadline, and thus Judge Glen Yamahiro granted default judgement to C.D. Smith. The company plans to submit a request for a foreclosure order on the property.

Design

The Edison is planned to be a 31-floor, 362 feet (110 m) tall luxury apartment tower, containing 357 units in various layouts, including studios and 3-bedroom dwellings. It will contain 7,000 square feet (650 m2) of ground-floor retail space, a parking garage containing 288 parking spaces for residents and visitors, and an amenity floor available to residents containing a spa, gym, pool, sauna, and health clinic available to residents, as well as a community garden on the roof. The design also features 2 public plazas placed on the side of the tower and along the Milwaukee river. Additional amenities including a spa, gym, pool, sauna, and health clinic available to residents, as well as a café, office space, and grocery store on the first floor,

Engineering of the Edison utilizes a hybrid structural system, employing cross-laminated timber panels over a concrete base to construct the building, and it is expected to use over 100,000 cubic feet of lumber. Cooling and heating will be handled via water-source heat pumps from the Milwaukee River to manage building temperatures and ventilation.

See also

References

  1. 1 2 3 4 Thibault, Matthew. "World's tallest mass timber building breaks ground in Wisconsin". Construction Dive. Retrieved 2026-09-07.
  2. 1 2 3 Jannene, Jeramey. "Stalled Downtown Apartment Tower Project Could Get New Owner". Urban Milwaukee. Retrieved 2026-09-07.
  3. 1 2 3 Shaver, Leslie (March 20, 2026). "Milwaukee mass timber project, billed as nation's tallest, reportedly faces foreclosure". Multifamily Dive. Retrieved 2026-09-07.
  4. 1 2 woodcentral (2026-07-10). "Court Clears Path to Sell Milwaukee's Stalled Edison Timber Tower". Wood Central. Retrieved 2026-09-07.
  5. ↑ Daykin, Tom. "A 15-story, 220-unit apartment development is being proposed for a downtown Milwaukee riverfront site by a Madison developer". Journal Sentinel. Retrieved 2025-03-06.
  6. ↑ Lanen, Bella Van (2025-01-08). "$133.3M secured for luxury downtown Milwaukee apartments". WISN. Retrieved 2025-03-06.
  7. 1 2 Mannion, Annemarie (July 14, 2026). "Contractor Wins $11.3M Judgment in Milwaukee Timber Tower Lawsuit". Engineering News-Record. Retrieved 2026-09-07.
  8. ↑ Turpin, Hunter (2025-01-07). "With financing closed, construction on The Edison could start in spring". BizTimes - Milwaukee Business News. Retrieved 2025-03-06.
  9. ↑ "What is mass timber construction & what are the benefits?". www.cdsmith.com. C. D. Smith Construction. Retrieved 2026-09-07.
  10. ↑ Daykin, Tom. "Halted Edison high-rise has $25 million cost gap. That could stop its Marcus development plan". Journal Sentinel. Retrieved 2026-10-19.
  11. ↑ "The Edison - The Skyscraper Center". www.skyscrapercenter.com. Retrieved 2026-09-07.
  12. ↑ Mannion, Annemarie (January 22, 2025). "Title of Tallest Mass Timber Building Could Come Back to Milwaukee". Engineering News-Record. Retrieved 2025-03-06.
  13. ↑ Daykin, Tom (2024-07-05). "A downtown high-rise is about to start construction. Public plazas are planned next to it". Milwaukee Journal Sentinel. Retrieved 2025-03-06.
  14. ↑ Ross, Jason (2025-01-08). "America's Next Timber Skyscraper to Use 100k Cubic Feet of Lumber!". Wood Central. Retrieved 2025-03-06.