Bucharest Metro Line M6

Line M6
Aeroportul Otopeni
Henri Coandă International Airport
Ion I.C. Brătianu
Otopeni
Bruxelles
Paris
Washington
Tokyo
Aeroportul Băneasa Aurel Vlaicu International Airport
Gara Băneasa Băneasa railway station
Piața Montreal
Expoziției
Pajura
under construction
existing infrastructure
1 Mai
Grivița
Basarab
Mainline rail interchange
Gara de Nord
Mainline rail interchange

Handicapped/disabled access All stations are accessible

M6 is an under construction metro line of the Bucharest Metro. The M6 Line will connect Bucharest North railway station (Gara de Nord) to Henri Coandă International Airport (Aeroportul Otopeni). The line is expected to be completed by 2028. Construction works have effectively started on December 15, 2023 and will be mainly financed by public funding, EU funds and JICA (Japan International Cooperation Agency), for a total cost estimated at €1.2 billion.

Stations

The M6 Line will have a total of 16 stations: 4 stations shared with the existing M4 Line and 12 planned new stations: Pajura, Expoziției, Piața Montreal, Gara Băneasa, Aeroport Băneasa, Tokyo, Washington, Paris, Bruxelles, Otopeni, Ion I.C. Brătianu, and Aeroport Otopeni.

PhaseTerminalsLengthTotal stationsConstruction sinceOpening
IGara de Nord – 1 Mai (as part of M4)3.6 km (2.2 mi)419892000
II1 Mai – Tokyo6.6 km (4.1 mi)6December 20232027 (est.)
IIITokyo – Otopeni Airport7.6 km (4.7 mi)6March 20252028 (est.)