It was announced by Prasarana Malaysia in 2013 and work began in 2016. Construction was halted in 2018 for a review that followed the change of government and concerns over funding. The project was later revived after it was reclassified from a rapid transit line to a light metro. Its expected completion was moved from 2020 to 2024. Continued delays then pushed the projected completion date through 2025 and eventually into 2026.
In May 2014, the Shah Alam LRT was proposed to begin from Bandar Utama, Kelana Jaya, running through areas of Glenmarie, HICOM-Glenmarie Industrial Park, Shah Alam Stadium, Shah Alam city centre, UiTM, I-City, Bukit Raja Shopping Centre, Taman Eng Ann, Bandar Klang and then heading straight on to Johan Setia. This was later confirmed in October 2015 following the tabling of Budget 2015 where the Prime Minister announced that the government will provide RM9 billion to build an LRT project linking Bandar Utama to Shah Alam and Klang.
Reception of approval
In 2015, the public display of the line will was held for three months beginning in May at seven locations – the offices of the Shah Alam City Council, Petaling Jaya City Council, Land Public Transport Agency, Klang Royal City Council (then known as Klang Municipal Council), as well as the Kelana Jaya, Masjid Jamek, and Pasar Seni LRT stations. It was also announced that construction works were to start by Q1-2016. In September 2015, Prasarana Malaysia Berhad announced that Malaysian Resources Corporation Berhad (MRCB) and George Kent Sdn Bhd joint venture (JV) has been appointed as the Project Delivery Partner (PDP) for the LRT project. In October 2015, Prasarana agreed to change the route of the LRT line, which was originally planned to cut through the housing area of Taman Muhibbah in Klang to Pasar Besar Klang (Klang wet market) at Jalan Meru. Residents of Taman Muhibbah had objected to the proposed line which would run through their housing area. The LRT project was officially launched by the sixth Malaysian Prime Minister Najib Razak in August 2016.
After the fall of the Barisan Nasional (BN)–led federal government in May 2018, the new Pakatan Harapan (PH)–led federal government, citing mounting national debt, proposed various cost-cutting measures to a list of federal government projects, including the LRT3 project. The Lien Hoe, Temasya, SIRIM, Bukit Raja and Bandar Botanik stations were reclassified to provisional stations while the underground station of Persiaran Hishamuddin was cancelled. The reasons cited for the changes made were due to the high cost of the project, unnecessary tunneling for the underground portion of the line and low ridership in the area. The provisional stations however will be built once demand in the area picks up.
Other cost-cutting exercises included the swapping of six-car trains for three-car trains, cutting down the total trains from 42 to 22, reducing the size of the stations to four-car length and ditching costly acceleration techniques. The completion date was also extended from 2020 to 2024.
Numerous delays and reinstatement of provisional stations
Fare gates at the concourse level of Bandar Utama station for Shah Alam Line service
The planned completion date of the entire line in 2024 as announced in 2018 was delayed for over two years due to the impact of the Malaysian movement control order from the COVID-19 pandemic and further testing of operations. The first delay for the overall opening of the line was announced in July 2023 where Transport MinisterAnthony Loke mentioned that the line was expected to be operational by 1 March 2025.
During the Budget 2024 presentation held on 13 October 2023, Finance MinisterAnwar Ibrahim announced the reintegration of the five stations that were previously under provisional status (Tropicana, Temasya, Raja Muda, Bukit Raja Selatan, Bandar Botanik) to be built alongside the rest of the Shah Alam Line with the exception of the sole underground station, Persiaran Hishamuddin, which remains cancelled.
In July 2024, the opening of the LRT line was further delayed to the third quarter of 2025. In February 2025, the opening of the LRT line was confirmed to be on 30 September 2025, with physical work reaching 98.16% completion. Construction was expected to be completed on 31 July and then handed over to Prasarana. Trial runs were to be conducted from mid-April to the end of June 2025. The total cost of the project was ultimately put at RM21.93 billion. In August 2025, the opening of the LRT line was delayed again for the fourth time, which is before the end of 2025, as further tests such as the fault-free run (FFR) test are still ongoing.
The delay was first teased by Prasarana through a social media post that the 24-hour train testing and commissioning activities of this line were ongoing until 31 October 2025, then further hinted on by a Prasarana internal memo, in which the company's CEO hoped for the line's opening in December 2025. It was finally confirmed by Transport Minister Loke, who stated that there were "slight delays", although he affirmed that he was confident that the line would be operational by 31 December 2025. However, the line was delayed once again to 2026 due to software glitches in the signalling system and the line's inability to complete the required fault-free run.
In February 2026, Transport Minister Loke confirmed that the LRT3 Shah Alam line is expected to begin operations by June 2026 at the latest. While Prasarana has set a conservative timeline for June, Loke expressed confidence that the line could be ready as early as April 2026, although this deadline was ultimately missed.
On 15 June 2026, Transport Minister Loke at the 62nd Annual General Meeting of the Malaysian Road Safety Council announced that the operations of the line is set to begin by month's end with the official date to be disclosed within the next two weeks, citing that the trial operations for the line have gone smoothly and the system is prepared for passenger service.
On 22 June 2026, Loke officially announced at the new Road Transport Department branch in Bandar Tasik Selatan that the line will begin full passenger operations on 29 June 2026 (Monday), with the opening ceremony to be officiated by Prime Minister Datuk Seri Anwar Ibrahim on 28 June 2026. Around the time of the line's launch ceremony, Prasarana's head of operations, Mohd Ariffin Idris and Loke mentioned that the previously provisional stations will begin construction by year's end and is targeted for opening in 2031. Prime Minister Anwar also mentions free fares (including train ride, feeder buses, and park & ride) for one month until 31 July 2026. On 31 July 2026, Rapid KL announced the free fares are extended until 14 August 2026.
Overview
Route
Route of Shah Alam Line
The line covers a span of 37.8 kilometres (23.5mi) from Bandar Utama to Johan Setia, passing through the cities of Petaling Jaya, Shah Alam, and Klang. The line serves more than 2 million residents within the western corridor of the Klang Valley region.
The line begins from Bandar Utama which is located near to the northwest borders of Kuala Lumpur and runs on an all-elevated guideway passing through villages of Kampung Sungai Kayu Ara, Tropicana, Subang, and the northeastern Shah Alam industrial areas of Glenmarie and HICOM-Industrial Park before serving the upcoming reconstruction of the Shah Alam Sports Complex in Section 13 via Stadium Shah Alam station. After that, the line continues into a 2.5 kilometres (1.6mi) underground tunnel before resurfacing nearby the Shah Alam city centre of Section 14 at Dato' Menteri, before running parallel to the New Klang Valley Expressway (NKVE) and serving Universiti Teknologi MARA (UiTM) and Section 7 before entering the district borders of Klang, serving Bandar Baru Klang, Kawasan 17, Klang city centre, Taman Sri Andalas, and Bandar Bukit Tinggi before terminating at Johan Setia.
There are also several stations equipped with Park N' Ride areas, either officially managed by Prasarana or by third-parties. For Park N' Rides managed by Prasarana, LRT-commuters will be charged RM 5.00 per entry and must use the same Touch 'n Go card when entering/exiting the parking area and boarding the trains.
Station designs
All of the operational stations are elevated, and is inspired by the concept theme of "tanjak" or "tengkolok" which is a symbol of Malaysian cultural heritage and splendor that combines traditional and modern elements, providing unique characteristic values. Of the 20 stations, two of them have a unique design from the rest, namely Stadium Shah Alam which is heavily decorated with sports-themed elements and consisting of a wider internal concourse area,[citation needed] and Dato' Menteri which has a different shade of blue as it is meant to resemble the trademark of the Shah Alam City Council (MBSA) on its exterior.[citation needed]
All stations are equipped with ticket vending machines, automatic bar entrance doors, information display systems (PIDS), feeder buses and on-demand transport information banners, as well as escalators, lifts, suraus, and toilets that are disabled-friendly and wheelchair accessible serving each platform.
List of stations
A Dynamic Route Map Display (DRMD) showing the train on its way northbound to Klang Jaya
Originally, a total of 26 stations were planned, with a proposed two-kilometre distance between each station. One station was to be an underground station, which was subsequently cancelled and instead turned into a tunnel ventilation control station. The other 25 stations are to be elevated.
The line currently has 25 permanent stations on this line with 20 stations opened on 29 June 2026, with the remaining five (5) previously reserved stations are expected to begin construction in the fourth quarter of 2026 and set to begin operations in 2031.
The Shah Alam line's fleet consists of 22 3-car trainsets from CRRC Zhuzhou. Operating at minimum headway frequencies, the fleet is capable of a maximum capacity of 18,630 passengers per hour per direction (pphpd) and is projected to carry 67,000 passengers per day once commercial service commences.
In 2024, it was announced that an additional seven 3-car trainsets would be added to the fleet by the end of 2027 as part of the cabinet's project scope restoration and the reinstatement of five previously shelved stations.
Rolling stock formation
The rolling stock consists of fully automated, driverless 3-car Light Rail Vehicles (LRVs) operating under Grade of Automation 4 (GoA4). Each trainset is configured in a three-car formation consisting of two motorized driving cars (Mc) sandwiching a middle unmotorized trailer car (T).
Car Position
Car Type
Driver's Cab
Traction Motors
Key Equipment & Operational Notes
Car 1
Mc1 (Motor Car)
No (Automated)
Yes
Trailing motor car housing automatic train control (ATC) equipment and propulsion systems.
Car 2
T (Trailer Car)
No
No
Center unmotorized trailer car housing static inverters (SIV) and primary air compressors.
Car 3
Mc2 (Motor Car)
No (Automated)
Yes
Leading motor car housing automatic train control (ATC) equipment and propulsion systems.
Fleet details
Configuration: Mc1 – T – Mc2
Total fleet size: 29 trainsets (22 delivered initially + 7 ordered for 2027 delivery).
Automation level: Driverless GoA4 technology without physical driver compartments, optimizing passenger panoramic views at the front and rear ends of the train.
Future expansion and platform proofing
Station platform future-proofing: All physical station platforms along the Shah Alam Line were built to a length capable of accommodating up to a 4-car trainset configuration in the future. This prevents costly infrastructure modifications or demolition down the line if demand scales up.
Current strategy focus: Despite the 4-car physical capability of the stations, all current supplemental rolling stock orders (including the 7 additional trainsets arriving by 2027) will remain strictly as 3-car trainsets. Prasarana's immediate plan for handling line demand growth relies entirely on reducing wait times and running higher-frequency headways with the 3-car sets.
Long-term 4-Car adjustments: The purchase of additional intermediate trailer cars to expand the existing fleet into a 4-car configuration will only be considered as a secondary phase in the future. This upgrade will only be triggered if rider capacity requirements grow to a point that high-frequency 3-car operations can no longer cope with peak travel demands.
Technical specifications
The rolling stock consists of lightweight, high-strength aluminum alloy car bodies engineered specifically with a narrow-profile cross-section to accommodate the line's infrastructure constraints.
Parameter
Specification
Notes
Total train length
57.60 m (189.0 ft)
End-to-end for a fully coupled 3-car formation (configured as Mc1–T–Mc2).
Individual car length
~19.2 m (63.0 ft)
Average per car body (~20 m overall including couplers).
Car width
2.65 m (8 ft 8 in)
Narrow-profile design tailored for medium-capacity transit infrastructure.
Car height
3.44 m (11 ft 3 in)
From top of rail head to vehicle roof line.
Track gauge
1,435 mm (4 ft 81⁄2 in)
Standard gauge.
Maximum operational speed
80 km/h (50 mph)
Commercial service cruising limit (Design speed capability up to 80 km/h).
Power supply
750 V DC
Power traction delivered via a bottom-contact third rail system.
Interior layout and seating configuration
The interior design optimizes passenger flow and maximizes standing room to meet the line's peak-direction throughput requirements.
Seating arrangement: Longitudinal perimeter seating (bench-style seating aligned flat against the cabin walls facing inward). This creates a wide central aisle to ease passenger boarding and offloading.
Seating material: Ergonomically contoured, cantilevered modular plastic seats designed for easy cleaning and high durability.
Gangway configuration: Fully open, continuous walkthrough gangways connect all three cars (inter-car accessibility), allowing passengers to move freely across the entire length of the train to distribute crowding evenly.
Accessibility (Disabled-friendly features):
Dedicated wheelchair and stroller mooring spaces equipped with safety backpads and grab straps.
Level-boarding thresholds designed to match seamless platform edge interfaces.
Passenger amenities:
Overhead longitudinal dynamic LED/LCD Passenger Information Displays (PIDS) providing real-time route maps, upcoming station announcements, and door opening orientation.
High-capacity, roof-mounted climate control HVAC units calibrated specifically for tropical environments.
Passenger capacity
The trains are engineered as a medium-capacity transit system designed to maintain high frequencies during peak commute hours.
Condition
Capacity per 3-car Trainset
Normal Passenger Load
~624 passengers
Crush Passenger Load
Up to 900+ passengers
Ridership
The line recorded 58,865 ridership on the first day of operations.
Shah Alam Line Ridership
Year
Month/Quarter
Ridership
Annual Ridership
Change (%)
Note
2026
Q4
4,193,490
-
Q3
4,079,915
As of September 2026
Q2
113,575
Opened on 29 June 2026
Q1
-
Other information
Initially, the Klang LRT station (now Jambatan Kota) was planned as an interchange station with the Klang Komuter station. However, due to cost-reduction efforts and objections from Little India Klang business residents, the station was built beside Emporium Makan and Shaw Centrepoint Mall, 700 meters away from the KTM Komuter station. This would have resulted in a same-name but different stations situation, similar to Salak Selatan LRT/KTM and Sentul LRT/KTM stations. The station has since been given a new name.
The trains will have a maximum operating speed of 80km/h (17% faster than the current LRT Kelana Jaya Line) with the capacity of carrying 36,720 passengers per hour per direction.
Gallery
Elevated LRT3 crossing under construction over the Klang River, running parallel with Kota Bridge, 2021.
A sign showing the destination of trains for each platform
Notes
↑The first delay was before the LRT3 cost restructuring and changed the estimated completion date from 2020 to 2024. The second delay was announced in 2023, further delaying the projected completion from 2024 to March 2025. The third delay was announced in 2024, where the date was pushed back from March 2025 to the third quarter of 2025. The fourth delay was announced in early 2025, with the date being pushed back further to 31 December 2025.
↑In early December, the opening of the line was delayed once again to 2026 due to software glitches in the signalling system and the line's inability to complete the required fault-free run.
↑Rapid KL (5 August 2021). "LRT3 kini dikenali sebagai LRT Laluan Shah Alam". Facebook (in Malay). Retrieved 23 September 2021. LRT3 atau dahulunya LRT Laluan Bandar Utama – Johan Setia, kini secara rasmi akan dikenali sebagai LRT Laluan Shah Alam.
↑"MY – Malaysia to Add a New LRT Line to Klang?". Bid Ocean Network.{{cite web}}: |access-date= requires |url= (help); |url= suppressed (help)CS1 maint: deprecated archival service (link)