Quito Metro

Quito Metro
Metro de Quito logo
Train arriving at Universidad Central station
Train arriving at Universidad Central station
Overview
Native nameMetro de Quito
LocaleQuito, Pichincha, Ecuador
Transit typeRapid transit
Number of lines
1
Number of stations
15
Daily ridership
350,000 (projected)
WebsiteMetro de Quito (in Spanish)
Operation
Began operation
1 December 2023; 2 years ago (1 December 2023)
OperatorEmpresa Pública Metropolitana Metro de Quito
Characterunderground
Number of vehicles
18
Technical
System length22.6 km (14.0 mi)
No. of tracks2
Track gauge1,435 mm (4 ft 8+1⁄2 in) standard gauge
Electrification1,500 V DC overhead wire
Average speed37 kilometres per hour (23 mph)
System map
Legend
Quitumbe
Morán Valverde
Solanda
Cardenal de la Torre
El Recreo
La Magdalena
San Francisco
La Alameda
El Ejido
Universidad Central
Pradera
La Carolina
Iñaquito
Jipijapa
El Labrador

The Quito Metro (Spanish: Metro de Quito), abbreviated as MDQ, is a rapid transit system consisting of a single line in Quito, the capital of Ecuador.

The Metro is part of Quito's long-term effort to improve public transportation and reduce traffic congestion. It integrates with other systems such as the Ecovía and Trolebús, and is operated by the municipal company Empresa Pública Metropolitana Metro de Quito.

History

Planning began in the late 2000s as part of a mobility master plan for the city. Construction started in 2013 and included tunnel boring and excavation through the historic center. The tunnels were completed by 2019. Construction of the metro line itself began in January 2016. The metro was projected to be operational by August 2020, but the opening was delayed numerous times.

The total cost of the project was estimated at US$2 billion. Funding was provided by multiple international institutions, including the Inter-American Development Bank (IDB), the World Bank, the European Investment Bank, and CAF.

The official inauguration was held on 21 December 2022, and commercial service started with some tests with passengers on 2 May 2023. After technical problems plagued the launch, service was shut down on 11 May. Later that year, the Quito metro initiated its commercial operations on 1 December 2023.

Operations

Service runs approximately every 5 to 10 minutes. The full journey from Quitumbe to El Labrador takes about 34 minutes. The system uses a contactless fare card integrated with the city’s bus networks.[citation needed ]

Network and stations

Lines

Line 1 connects the southern terminal at Quitumbe with the northern station at El Labrador, spanning 22.6 km entirely underground. It has 15 stations and is the backbone of the city's rapid transit system.

Stations

The system's first line, which includes 15 stations, extends from Quitumbe in the south of the city to El Labrador in the north of the city. The 15 stations on this line are, from south to north:

Image Station Neighborhood Connections Serves
QuitumbeQuitumbeSouthern intercity bus terminal
Morán ValverdeChillogalloUrban buses
SolandaSolandaFeeder bus lines
Cardenal de la TorreChimbacalleTrolleybus
El RecreoLa MagdalenaEcovía
La MagdalenaLocal buses
San FranciscoHistoric Center Tourist zone
La AlamedaItchimbíaTrolleybus
El EjidoMariscalTrolleybus Universities
Universidad CentralUniversidad Central University of Ecuador
PraderaIñaquito Business and hotel district
La Carolina Carolina Park, shopping centers
Iñaquito Public offices
JipijapaJipijapa Local buses
El LabradorEl LabradorPlanned intermodal terminal

The station at Plaza de San Francisco (by the San Francisco monastery), is the only station placed in the historic center of Quito (declared a World Heritage Site by UNESCO in 1978). Due to archaeological remains found at the proposed site of the San Francisco station in late 2016, the station was moved two blocks further south to the Plaza 24th of May, and the remains will not be disturbed further.[citation needed ]

Every station is painted in a distinct color to help with passenger orientation.

The design of Line 1 allows for five infill stations to be built if demand warrants, and for a potential 5 km extension northwards to the Ofelia bus terminal.[citation needed ]

Rolling stock

Line 1 operates 18 trains manufactured by CAF. Each train has six cars and can carry up to 1,500 passengers. The trains are equipped with air conditioning, CCTV, and accessibility features.

Network map