The Seibi Shinkansen (整備新幹線; "Development Shinkansen") refers to five planned routes of Shinkansen, a High-speed rail of Japan, for which the Japanese government announced the basic plan in 1972 pursuant to Article 7 of the Nationwide Shinkansen Railway Development Act (全国新幹線鉄道整備法, Zenkoku Shinkansen Tetsudō Seibihō) (Act No. 71 of 1970), and subsequently approved the development plan on November 13, 1973. At the time, these lines were often referred to as the Seibi Go-sen (整備5線; "Five Development Lines") or Seibi Go Shinkansen (整備5新幹線; "Five Development Shinkansen Lines"), but today the term "Seibi Shinkansen" has become the standard designation.
| Line name | Japanese | Start | Terminal | Major cities along route | Length | Status | Sections in operation | Sections under construction (Planned opening) |
Sections not yet started |
|---|---|---|---|---|---|---|---|---|---|
| Hokkaidō Shinkansen | 北海道新幹線 | Aomori, Aomori | Sapporo, Hokkaido | Near Hakodate and Otaru | 360 km | Partially open | Shin-Aomori — Shin-Hakodate-Hokuto | Shin-Hakodate-Hokuto — Sapporo (Scheduled for completion by FY2038) |
|
| Tōhoku Shinkansen | 東北新幹線 | Morioka, Iwate | Aomori, Aomori | Near Hachinohe | 179 km | Fully open | Morioka — Shin-Aomori | ||
| Hokuriku Shinkansen | 北陸新幹線 | Tokyo | Osaka, Osaka | Near Nagano, Toyama, and Obama | 600 km | Partially open | Tokyo — Tsuruga | Tsuruga — Shin-Osaka | |
| Kyūshū Shinkansen (Kagoshima Route) | 九州新幹線(鹿児島ルート) | Fukuoka, Fukuoka | Kagoshima, Kagoshima | Near Kumamoto and Satsumasendai | 257 km | Fully open | Hakata — Kagoshima-Chūō | ||
| Kyūshū Shinkansen (West Kyūshū Route) | 九州新幹線(西九州ルート) | Fukuoka, Fukuoka | Nagasaki, Nagasaki | Near Saga | 118 km | Partially open | Hakata — Shin-Tosu Takeo-Onsen — Nagasaki |
Shin-Tosu — Takeo-Onsen |

The following earlier Shinkansen lines — Tōkaidō Shinkansen, Sanyō Shinkansen, Tōhoku Shinkansen (Tokyo — Morioka section), Jōetsu Shinkansen, and the Narita Shinkansen (whose plan was later canceled) — are not included among the Seibi Shinkansen.
Similarly, the twelve Kihon Keikaku Rosen (基本計画路線; "Basic Plan Lines"), whose basic plans were announced on November 15, 1973—one year later than the Seibi Shinkansen—are not included in the Seibi Shinkansen category. Of these twelve lines, only the maglev Chūō Shinkansen, for which the development plan was approved in May 2011, has actually commenced construction to date.
In 1970, the Nationwide Shinkansen Railway Development Act (全国新幹線鉄道整備法) was enacted. Under this law, the construction of Shinkansen lines was promoted with the aims of fostering economic development and regional revitalization of Japan.
Based on the Act, the following routes were officially designated as part of the national basic plan:
On November 13, 1973, the Minister of Transport approved the construction plans for five Shinkansen lines.
| Line | Propulsion system | Maximum design speed | Estimated construction cost (including rolling stock) | Construction body | Notes |
|---|---|---|---|---|---|
| Tōhoku Shinkansen | EMU using adhesion drive | 260 km/h | ¥330 billion | JNR | |
| Hokkaidō Shinkansen | ¥630 billion | JRCPC | 1. The Hokkaidō Shinkansen shares the Seikan Tunnel section with the Tsugaru Kaikyō Line. 2. The estimated cost does not include the expenses for the Tsugaru Kaikyō Line works. | ||
| Hokuriku Shinkansen | ¥1.17 trillion | JRCPC | The section between Tokyo and Takasaki is shared with the Jōetsu Shinkansen. | ||
| Kyūshū Shinkansen (Fukuoka — Kagoshima) | ¥445 billion | JNR | |||
| Kyūshū Shinkansen (Fukuoka — Nagasaki) | ¥215 billion | JNR | 1. The line diverges from the Kyūshū Shinkansen (Fukuoka — Kagoshima) in the Chikushi Plain, sharing the section from Fukuoka to the divergence point. 2. The estimated cost excludes the shared section with the Fukuoka — Kagoshima route. |
In 1988, the Ministry of Transport (MOT, the current MLIT) announced what became known as the "MOT Proposal (運輸省案)". This plan aimed to reduce construction costs while achieving higher operating speeds by combining different construction methods, such as the Mini-Shinkansen system and the Super Tokkyū concept. Under this policy, construction began on sections of three lines — the Tōhoku, Hokuriku, and Kyūshū (Kagoshima Route) Shinkansen — marking the first major progress in the Seibi Shinkansen project since its designation in the 1970s.
The proposed plan was met with strong criticism from local governments and politicians along the designated construction sections. The Governor of Toyama Prefecture at the time criticized this, stating that it was like "I ordered eel (a full-standard Shinkansen) but the restaurant served me conger (Mini Shinkansen) or loach (Super Tokkyū) instead", reflecting widespread dissatisfaction. Nevertheless, since it was unclear when the next opportunity for new Shinkansen construction would arise if this one were missed, local authorities reluctantly accepted the plan. Later that same year, the government and ruling parties agreed on the construction priority order as follows:
1. Hokuriku Shinkansen: Takasaki — Nagano (Takasaki — Karuizawa: Full-standard, Karuizawa — Nagano: Mini-Shinkansen. However, if Nagano were selected to host the Winter Olympics, conversion to full-standard would be considered.)
1. Hokuriku Shinkansen: Takaoka — Kanazawa: Super Tokkyū.
2. Tōhoku Shinkansen: Morioka — Aomori (Numakunai — Hachinohe: Full-standard, Sections before and after: Mini-Shinkansen)
3. Kyūshū Shinkansen (Kagoshima Route): Yatsushiro — Nishi-Kagoshima : Super Tokkyū
4. Hokuriku Shinkansen: Itoigawa — Uozu: Super Tokkyū
However, due to limited national funding for Shinkansen construction, only the highest-priority section, the full-standard Takasaki — Karuizawa segment, began construction the following year in 1989. The remaining sections did not commence until after 1991, when the proceeds from the transfer of existing Shinkansen lines (see the section on the "Old funding scheme") became a designated financial source for new Shinkansen construction.
In 1991, following the decision at the International Olympic Committee General Assembly held in Birmingham, United Kingdom, to award the 1998 Winter Olympics to Nagano, the section between Karuizawa — Nagano was upgraded from the planned Mini-Shinkansen to a full-standard Shinkansen.
Meanwhile, for the Takaoka — Kanazawa section, which had the same construction priority ranking, opposition arose from local municipalities in Toyama Prefecture along the Hokuriku Main Line (Isurugi — Takaoka section), which was to be separated from JR as a heikō zairaisen (parallel conventional line). As a result, the planned route was modified to run between Shin-Takaoka — Kanazawa, and the construction section was shortened to Isurugi — Kanazawa.
In 1994, during the scheduled five-year review of Shinkansen construction plans, momentum grew for authorizing new projects. However, funding constraints again became a major obstacle. Consequently, the Tōhoku Shinkansen Morioka — Numakunai section, which had originally been planned as a Mini-Shinkansen, was upgraded to full-standard, while the start of construction on the Hachinohe — Aomori section was postponed.
In 1996, a new funding policy was introduced. This framework utilized property tax reduction measures (50% reduction) granted to the three JR companies on Honshū (JR East, JR Central, and JR West) as a financial resource for new Shinkansen construction. This led to renewed momentum for selecting new construction sections.
On December 25, 1996, the government–ruling party committee agreed to select three candidate sections across three Shinkansen lines. After profitability studies and evaluations by the Government–Ruling Party Committee for Seibi Shinkansen Development (政府・与党整備新幹線検討委員会), the construction authorization and priority order were finalized on January 21, 1998. Construction on these sections officially began in March 1998.
1. Tōhoku Shinkansen: Hachinohe — Shin-Aomori: Full-standard
1. Kyūshū Shinkansen (Kagoshima Route): Funagoya — Shin-Yatsushiro: Super Tokkyū
2. Hokuriku Shinkansen: Nagano — Jōetsu : Full-standard
In 1999, with the formation of the Liberal Democratic Party (LDP)–Liberal Party and later the LDP–Liberal–Komeito coalition governments, a new review of Shinkansen development policy was undertaken. The resulting proposal called for both upgrading partially constructed sections to full-standard specifications and starting construction on new sections. In 2000, MOT requested in its FY2001 budget proposal the initiation of new construction for the Hokuriku Shinkansen section between Jōetsu — Itoigawa, and the Kyūshū Shinkansen section between Hakata — Funagoya.
Subsequently, a government–ruling party agreement finalized the decision to begin new construction on two lines (three sections), adding the Shin-Kurobe — Toyama section to the Hokuriku Shinkansen plan.
On March 13, 2004, the section of the Kyūshū Shinkansen between Shin-Yatsushiro — Kagoshima-Chūō opened for service. Around the same time, review work was conducted in preparation for new construction starts. On June 10, 2004, the ruling parties' Shinkansen Construction Promotion Project Team reached an agreement that finalized three new sections (or four if including the section around Fukui Station) to be newly constructed.
In 2005, new construction began on the Hokkaidō Shinkansen and Hokuriku Shinkansen sections. As for the Nagasaki (West Kyūshū) Route, construction was delayed because local municipalities along the section of the heikō zairaisen (parallel conventional line) — the Nagasaki Main Line between Hizen-Yamaguchi — Isahaya — specifically Kōhoku Town and Kashima City in Saga Prefecture, opposed the management separation of the line. Although the national government allocated about 1 billion yen annually for the project from 2005 onward as part of public works expenditures, construction could not begin, and the budget remained unused. Subsequently, in December 2007, a so-called "three-party agreement" was reached among Saga Prefecture, Nagasaki Prefecture, and JR Kyūshū, adopting a "vertical separation model", under which JR Kyūshū would continue operating the heikō zairaisen section for 20 years after the Shinkansen opened. Following this agreement, official construction approval was granted in March 2008, and work commenced the following month in April.

Following the change of government in September 2009 from the Liberal Democratic Party (LDP) to the Democratic Party of Japan (DPJ), a major review of public works projects was carried out. As a result, construction of the unstarted sections of the Hokkaido, Hokuriku, and Kyūshū (West Kyūshū Route) Shinkansen lines was temporarily frozen. These sections faced significant challenges, including enormous construction costs and difficulties in reaching agreements with local municipalities along the routes regarding the separation of heikō zairaisen.
However, progress was made toward securing financial resources by allocating the track usage fees paid by JR companies to construction funding, and negotiations with local governments along the planned routes advanced. In addition, after the Great East Japan Earthquake in 2011, national policy shifted toward focusing on strengthening core infrastructure. Consequently, at the end of 2011, the Ministry of Land, Infrastructure, Transport and Tourism (MLIT) announced its intention to begin construction on the following three sections, on the condition that agreements be reached with local governments along the routes:
Official approval for construction was granted on June 29, 2012. The target completion years were set as fiscal 2035 for the Hokkaidō Shinkansen, 2025 for the Hokuriku Shinkansen, and 2022 for the Kyūshū Shinkansen West Kyūshū Route , including the already started section between Takeo-Onsen — Isahaya. Subsequently, under the restored LDP administration, an accelerated schedule for construction was officially decided on January 14, 2015.
As of April 2026, the following sections of the Seibi Shinkansen network remain unstarted:
Under the Seibi Shinkansen framework, it is stipulated that construction cannot be commenced unless the following five conditions are satisfied:
As will be discussed in detail later, several route options have been considered for each of the two remaining sections. However, for these remaining sections, many of the proposed routes yield unfavorable figures in terms of financial viability and cost–benefit performance, partly due to the recent surge in construction costs.
In addition, under the Seibi Shinkansen scheme, a portion of the construction cost is to be borne by local governments along the route. However, this cost allocation is not based on the degree of benefit received by each prefecture, but rather on a strictly territorial basis. In other words, even if a given prefecture has limited need for the line, it is still required to bear (a portion of) the construction cost for the section passing through its territory. As a result, such prefectures tend to be reluctant toward those route options (e.g., Shiga Prefecture in the Maibara Route proposal for the Hokuriku Shinkansen ).
Furthermore, under the Seibi Shinkansen scheme, the separation of heikō zairaisen—whereby they are transferred to third-sector railway companies funded by local governments—is permitted. This creates the possibility that a prefecture may be required not only to bear the construction costs of a Shinkansen line it does not need, but also to assume responsibility for loss-making conventional lines (e.g., Saga Prefecture in the case of the Nishi Kyūshū Shinkansen ). As a result, the condition of obtaining the consent of all affected local governments has become a particularly high hurdle for many current route proposals.
In addition, since the division and privatization of Japanese National Railways, each JR company has continued to operate as a completely separate corporation, and their interests do not necessarily align. As a result, for example, if a route proposal involves through-running onto another Shinkansen line operated by a different JR company partway along the route, obtaining the consent of the JR company designated as the operating entity can become difficult, since the revenue from that section would effectively accrue to the other company.

The section of Hokuriku Shinkansen between Tsuruga — Shin-Osaka remain unstarted. Up to this point, various route options for this section have been considered. The following are the main proposed routes.
At first, the Maibara Route was considered, but it was soon replaced by the Obama Route, and by the time the Seibi Shinkansen plan was formulated in 1972, this was the route that had been envisioned. (The Maibara Route remained as a separate plan under the name "Hokuriku–Chūkyō Shinkansen", distinct from the Hokuriku Shinkansen.)
In addition, at one point, a plan was also considered to use a Free Gauge Train (FGT) via the Kosei Route. However, at a meeting between the government, the ruling parties, and JR West on August 24, 2018, it was decided to abandon the introduction of FGT, citing "technical difficulties and delays in development".
Ultimately, in 2016, it was decided that development would proceed based on the Obama–Kyoto Route, which modified the previous Obama Route by changing the line's passage through Kyoto Prefecture from Kameoka to Kyoto. The following year, in 2017, it was further decided that the section between Kyoto and Shin-Osaka would follow the so-called Southern Route (南回りルート, Minami-mawari Rūto), passing via Matsuiyamate Station in the southern part of Kyoto Prefecture.
There have also been proposals regarding the Osaka-side terminus, including locating it at Tennōji instead of Shin-Osaka, or extending the line further to Kansai International Airport. However, in April 2016, a ruling party committee formally decided that the Osaka-side terminus would be Shin-Osaka.
As a result of these processes, the route of the Hokuriku Shinkansen west of Tsuruga was determined to follow the Obama–Kyoto Route, and from Kyoto Station it would proceed to Shin-Osaka via the Southern Route passing through Matsuiyamate.
However, even as of April 2026—ten years after the route for the extension section was decided as the Obama–Kyoto Route—construction on this section has yet to begin. In the process of examining the detailed alignment, it has become clear that costs will be significantly higher than initially expected and that the construction period will be longer. Furthermore, opposition movements against this route also began to emerge, particularly in Kyoto (discussed later).
Amid these developments, there has been some movement calling for a reconsideration of the once-decided route. Some organizations, including Ishikawa Prefecture and Japan Innovation Party (JIP), support the Maibara Route instead.
On December 15, 2025, following a change in the ruling coalition framework from LDP–Komeito alliance to one between LDP and JIP, LDP agreed to examine eight proposals advocated by JIP. From 2026 onward, hearings will be conducted with the operating company JR West and local governments along the line, and a request will be made to MLIT to recalculate the cost-effectiveness.
However, as outlined below, each of the proposed routes has its own advantages and disadvantages, and the reality is that even if the Obama–Kyoto Route has problems, the alternative options cannot be chosen easily either:
Each of these routes has its own advantages and disadvantages, and JR West continues to support the once-selected Obama–Kyoto Route.
The Kyūshū Shinkansen (West Kyūshū Route) experienced significant delays due to the prolonged development and cancellation of the FGT, a variable gauge train that was initially planned for introduction on the line. As a result, the originally scheduled opening, set for fiscal year 2022, was officially postponed to fiscal year 2025 or later. Subsequently, as an interim measure, the MLIT adopted a "relay system", under which conventional limited express trains operate between Hakata — Shin-Tosu — Takeo-Onsen, while Shinkansen trains operate between Takeo-Onsen — Nagasaki. The latter section opened as the Nishi Kyūshū Shinkansen on September 23, 2022.
The section between Shin-Tosu — Takeo-Onsen remain unstarted. Saga Prefecture, the prefecture along this section, is already located sufficiently close to the major city of Fukuoka and has never considered a full-standard Shinkansen to be necessary. Rather, it is concerned about potential declines in service on heikō zairaisen (parallel conventional lines) and the financial burden on local governments resulting from the separation of JR operations if a Seibi Shinkansen is built. For this reason, Saga Prefecture had taken the position that it would only accept an FGT operating on conventional lines. However, since the FGT plan has now been abandoned, the national government and Nagasaki Prefecture are seeking to complete the section between Shin-Tosu — Takeo-Onsen as a full-standard Shinkansen line. Saga Prefecture, however, has never requested a full-standard Shinkansen and does not consider it necessary even now. As a result, a conflict has arisen, with Saga Prefecture arguing that "this differs from what was originally agreed in the past".
The national government (the MLIT) and Saga Prefecture have held several rounds of the "Broad Consultations" (幅広い協議) on this issue since June 2020. In these discussions, Saga Prefecture reaffirmed its position that it had not accepted the construction of the line to full Shinkansen standards. However, on that basis, regarding the following three proposals put forward by the Railway Bureau of the MLIT, Saga Prefecture proposed that the national government examine whether any of them contained points worthy of consideration by the prefecture:
Of these options, the Southern Route has attracted interest from the Kurume Chamber of Commerce and Industry. However, the MLIT considers it "technically difficult". Since passing near Saga Airport along the coastline would require bridges or tunnels, construction is deemed challenging due to height restrictions around the airport, as well as concerns about impacts on fisheries and safety. In addition, JR Kyūshū has stated that, considering that the Southern Route would also impose financial burdens on Fukuoka Prefecture, the Saga Station Route is the most preferable among the three options.
The Tōhoku and Jōetsu Shinkansen lines were constructed using JNR's own funds and loans from the Fiscal Investment and Loan Program (FILP), which ultimately contributed to the ballooning of JNR's debt. Reflecting on this experience, the subsequent Seibi Shinkansen lines were built in principle as public works projects financed by non-repayable funds from the national and local governments. Accordingly, each section of the Seibi Shinkansen is owned by the Japan Railway Construction, Transport and Technology Agency (JRTT), an independent administrative agency under the Ministry of Land, Infrastructure, Transport and Tourism (MLIT), while the JR companies operate the trains by paying track usage fees to reflect the benefits they gained after the line's opening.
However, the Ministry of Finance (formerly the Ministry of Finance and Treasury) strongly resisted increases in public works spending, meaning that every new construction start or schedule acceleration required the identification of new funding sources.
When construction began on the Hokuriku Shinkansen (Takasaki — Karuizawa section) in 1989, the following cost-sharing arrangement was established:
In 1990, as the sale of the existing Shinkansen lines to JR East, JR Central, and JR West was scheduled for the following year, a special funding source for the Seibi Shinkansen projects was established. Specifically, ¥1.1 trillion—the amount added through the asset revaluation accompanying the transfer—was designated as a special revenue source. From this, ¥72 billion per year was allocated to both the national government and the JR companies (as a replacement for the surplus from the lease revenues of the existing Shinkansen lines).
As an exception, the Hokuriku Shinkansen (Takasaki — Nagano section) received ¥278 billion in FILP funds, which are repayable, in order to ensure the line opened in time for the Nagano Winter Olympics. Since opening, the loan repayments have been made using track usage fees from the operational sections of the Tōhoku and Kyūshū Shinkansen lines, meaning that very little of these fees could be used toward new construction costs. However, with the enactment of the Amended JNR Debt Settlement Act (改正国鉄債務処理法) on June 8, 2011, debts were repaid using the retained earnings from the special accounts of the JRTT. As a result, the funds that had been used for debt repayment could now be redirected toward construction costs.
In 1996, with the launch of construction on three sections of three Shinkansen lines, the cost-sharing framework among the national government, local governments, and the JR companies was revised as follows:
At the end of 2004, the government and ruling coalition agreed to accelerate the use of revenue from the sale of existing Shinkansen assets, applying funds originally scheduled for use after fiscal 2013 to ongoing construction projects.
Furthermore, during profitability simulations for the Hokuriku Shinkansen (Toyama — Kanazawa) and Hokkaidō Shinkansen (Shin-Aomori — Shin-Hakodate-Hokuto), it was found that JR East, which would operate trains across company boundaries, would gain significant additional profits—estimated at ¥39 billion per year for the Hokuriku Shinkansen and ¥22 billion per year for the Hokkaidō Shinkansen. Consequently, a policy was introduced requiring JR East to bear a portion of these "base benefits (根元受益)" as part of the financial contribution. Although JR East initially resisted this arrangement, subsequent negotiations with the JRTT resulted in an increase in track usage fees upon the opening of the Shin-Aomori — Shin-Hakodate-Hokuto section.
| 1989 | 6.3 |
| |
| 1990 | 21.1 |
| |
| 1991 | 37.3 |
| |
| 1992 | 129.6 |
| |
| 1993 | 192.2 |
| |
| 1994 | 194.2 |
| |
| 1995 | 254.8 |
| |
| 1996 | 172.5 |
| |
| 1997 | 148.2 |
| |
| 1998 | 189.9 |
| |
| 1999 | 237.9 |
| |
| 2000 | 275.3 |
| |
| 2001 | 291.6 |
| |
| 2002 | 238.0 |
| |
| 2003 | 207.2 |
| |
| 2004 | 220.7 |
| |
| 2005 | 225.3 |
| |
| 2006 | 250.9 |
| |
| 2007 | 268.7 |
| |
| 2008 | 317.8 |
| |
| 2009 | 366.6 |
| |
| 2010 | 251.0 |
|
| FY | Total cost | |||||
|---|---|---|---|---|---|---|
| 2007 | - |
| ||||
| 2008 | - |
| ||||
| 2009 | - |
| ||||
| 2010 | - |
| ||||
| 2011 | - |
| ||||
| 2012 | - |
| ||||
| 2018 | 225.3 |
| ||||
| 2019 | 226.6 |
| ||||
| 2020 | 225.4 |
| ||||
| 2021 | 231.2 |
| ||||
| 2022 | 233.4 |
| ||||
| 2023 | 242.1 |
| ||||
| 2024 | 227.5 |
|
For the Seibi Shinkansen lines, by agreement between the local governments along the route and JR, the heikō zairaisen (並行在来線; "parallel conventional lines") —existing conventional railway lines running along the same corridor, are to be separated from JR's management and either converted into third-sector railways (jointly funded by local governments and private entities) or discontinued. This measure aims to reduce JR's management burden, as it would be financially difficult for JR to operate both the costly new Shinkansen facilities and the local conventional lines that would lose traffic and become underused after the Shinkansen's opening. However, there are some sections that have remained under JR management. According to the "Government–Ruling Party Agreement on the Handling of Shinkansen Development Lines (整備新幹線の取扱いについて 政府与党合意)" dated December 25, 1996, it was confirmed that "For the sections of the Seibi Shinkansen lines to be newly constructed, the corresponding heikō zairaisen shall, as before, be separated from JR management upon the opening of the Shinkansen". Thus, the same measure is planned for the heikō zairaisen corresponding to Shinkansen sections yet to open. For these heikō zairaisen, key challenges include how to maintain service for local passengers, how to handle freight train operations and branch lines connected to the parallel lines, and how to ensure the financial viability of the new third-sector operators. As of the opening of the Hokuriku Shinkansen section between Kanazawa — Tsuruga in 2024, the only heikō zairaisen that has been fully discontinued is the section of the Shinetsu Main Line between Yokokawa — Karuizawa.
| Seibi Shinkansen | Before Shinkansen opening | Section | Operating distance | Date of transfer/abolition | After Shinkansen opening | |
|---|---|---|---|---|---|---|
| Hokkaidō Shinkansen | JR East | Tsugaru Line | Aomori — Mimmaya | 55.8 | Remains under JR East management (Shinkansen and conventional line are managed by different JR companies) | |
| JR Hokkaidō | Kaikyō Line | Naka-Oguni — Kikonai | 87.8 | Remains under JR Hokkaidō management (regular passenger services discontinued; only freight trains and cruise-style tourist trains operate) | ||
| Esashi Line | Kikonai — Goryōkaku | 37.8 | March 26, 2016 | Transferred to South Hokkaidō Railway (electrification retained; regular passenger services operated with diesel trains) | ||
| Hakodate Main Line | Hakodate — Shin-Hakodate-Hokuto | 17.9 | FY2030 | Remained under JR Hokkaidō after opening of Shin-Aomori — Shin-Hakodate-Hokuto section; to be separated from JR Hokkaidō after opening of Shin-Hakodate-Hokuto — Sapporo section | ||
| Shin-Hakodate-Hokuto — Oshamambe Ōnuma — Shikabe — Mori |
129.7 | Scheduled for separation from JR Hokkaidō management; future handling undecided as of 2026 | ||||
| Oshamambe — Otaru | 140.2 | Scheduled for abolition (to be replaced by bus service) | ||||
| Otaru — Sapporo | 33.8 | Planned to remain under JR Hokkaidō management | ||||
| Tōhoku Shinkansen | JR East | Tōhoku Main Line | Morioka — Metoki | 82.0 | December 1, 2002 | Transferred to IGR Iwate Galaxy Railway |
| Metoki — Hachinohe | 25.9 | Transferred to Aomori Prefecture and Aoimori Railway (vertical separation model) | ||||
| Hachinohe — Aomori | 96.0 | December 4, 2010 | ||||
| Hokuriku Shinkansen | JR East | Shinetsu Main Line | Takasaki — Yokokawa | 29.7 | Remains under JR East management | |
| Yokokawa — Karuizawa | 11.2 | October 1, 1997 | Abolished (replaced by JR Bus Kantō's Usui Line bus service) | |||
| Karuizawa — Shinonoi | 65.1 | Transferred to Shinano Railway | ||||
| Shinonoi — Nagano | 9.3 | Remains under JR East management | ||||
| Nagano — Myōkō-Kōgen | 37.3 | March 14, 2015 | Transferred to Shinano Railway | |||
| Myōkō-Kōgen — Naoetsu | 37.7 | Transferred to Echigo Tokimeki Railway | ||||
| JR West | Hokuriku Main Line | Naoetsu — Ichiburi | 59.3 | March 14, 2015 | Transferred to Echigo Tokimeki Railway (electrification retained; regular passenger trains operated by diesel units) | |
| Ichiburi — Kurikara | 100.1 | Transferred to Ainokaze Toyama Railway | ||||
| Kurikara — Kanazawa | 17.8 | Transferred to IR Ishikawa Railway | ||||
| Kanazawa — Daishōji | 46.4 | March 16, 2024 |
Transferred to IR Ishikawa Railway | |||
| Daishōji — Tsuruga | 84.3 | Transferred to Hapi-Line Fukui | ||||
| Kyūshū Shinkansen (Kagoshima Route) | JR Kyūshū | Kagoshima Main Line | Hakata — Yatsushiro | 154.1 | Remains under JR Kyūshū management | |
| Yatsushiro — Sendai | 116.9 | March 13, 2004 | Transferred to Hisatsu Orange Railway (electrification retained; regular passenger trains operated by diesel units) | |||
| Sendai — Nishi-Kagoshima | 46.1 | Remains under JR Kyūshū management | ||||
| Kyūshū Shinkansen (West Kyūshū Route) | Nagasaki Main Line | Hizen-Yamaguchi — Isahaya Station | 60.8 | September 23, 2022 | For 23 years after opening, operates under a vertical separation model: the facilities are managed by the Saga–Nagasaki Railway Management Center (佐賀・長崎鉄道管理センター) (jointly funded by Saga and Nagasaki Prefectures), while JR Kyūshū operates the trains. Electrification between Hizen-Hama — Isahaya has been discontinued. | |
| Isahaya — Ichibu — Nagasaki Kikitsu — Nagayo — Urakami |
48.4 | Remains under JR Kyūshū management (electrification discontinued) | ||||
In preparation for the opening of the section between Shin-Aomori — Shin-Hakodate-Hokuto, one major issue concerned how to handle the Esashi Line. While it had been agreed that the section between Kikonai — Goryōkaku, which runs parallel to the Shinkansen line, would be separated from JR management, the non-electrified section between Kikonai — Esashi, which does not run parallel to the Shinkansen line, would have become a line disconnected from the rest of the JR's conventional network. Moreover, it was one of the sections within JR Hokkaido's area with extremely low passenger numbers. For these reasons, this section was abolished on May 12, 2014.
Meanwhile, in August 2014, the South Hokkaidō Parallel Conventional Line Preparation Company (北海道道南地域並行在来線準備株式会社) (the predecessor of South Hokkaidō Railway) was established. With the opening of the Hokkaidō Shinkansen on March 26, 2016, the section between Kikonai — Goryōkaku was transferred to South Hokkaidō Railway.
As for the Tsugaru Line, Aomori Prefecture expressed the view that "since JR East operates the Tsugaru Line and JR Hokkaidō operates the Hokkaidō Shinkansen, the line is not subject to separation". JR East also confirmed in 2004 that the line would not be separated from its management.
However, after a torrential rain disaster in August 2022, the section between Kanita — Minmaya was rendered impassable. Because restoration costs are estimated at a minimum of 600 million yen, discussions have begun on the possibility of abolishing the closed section. Subsequently, in March 2025, Aomori Prefecture, JR East, and the municipalities along the line agreed to discontinue passenger railway services between Kanita — Minmaya in April 2027 and convert the route to road-based transportation. (However, the section between Kanita Station — Shin-Naka-Oguni Signal Station will remain in operation as a freight line.)
The section between Hakodate — Shin-Hakodate-Hokuto is used by the Hakodate Liner, a shuttle service providing access between the new station on the Hokkaidō Shinkansen and the central conventional station in Hakodate. Hakodate City and the Hakodate Chamber of Commerce and Industry requested that this section not be separated from JR Hokkaidō 's management and that JR Hokkaidō continue to operate it even after the Shinkansen is extended to Sapporo.
In response, JR Hokkaidō announced that it would continue to operate the section between Otaru — Sapporo, but it did not indicate any policy to continue operation of the section between Shin-Hakodate-Hokuto — Hakodate. JR Hokkaidō also stated that agreement on the separation of management for the Hakodate — Otaru section was an indispensable condition for the authorization and commencement of construction of the Shinkansen extension. As a result, the local governments along the line, including Hakodate City, ultimately agreed to the separation of management for this section.
On February 3, 2022, it was decided that within the Hakodate — Otaru section, the portion between Oshamambe — Yoichi would be abolished and replaced by bus service, as maintaining the railway would cause significant financial losses due to high maintenance costs. The discontinuation of a heikō zairaisen following the opening of a new Shinkansen section marks the second such case, after the closure of the Yokokawa — Karuizawa section of the Shinetsu Main Line when the Hokuriku Shinkansen (Takasaki — Nagano) opened on October 1, 1997.
Meanwhile, regarding the section between Yoichi — Otaru, Yoichi Town, where many residents commute to and from Otaru, insisted on maintaining railway operations through a third-sector railway. However, discussions with Otaru City, which also considered bus conversion, did not reach an agreement, and the decision was postponed. Eventually, on March 26, 2022, Hokkaidō Prefecture, Otaru City, and Yoichi Town reached an agreement to convert the section to bus service. The following day, on March 27, Hokkaidō and the nine municipalities along the line agreed to the abolition and bus conversion of the entire Oshamambe — Otaru section.
On December 1, 2002, the section between Morioka — Hachinohe opened, and management of the corresponding section of the Tōhoku Main Line between Morioka — Metoki was transferred to the third-sector railway operator IGR Iwate Galaxy Railway (Category-1 Railway Business Operator ), while the section between Metoki — Hachinohe was transferred to Aomori Prefecture (Category-3 Railway Business Operator ) and Aoimori Railway (Category-2 Railway Business Operator ). Later, on December 4, 2010, the line was extended from Hachinohe to Shin-Aomori Station, and the section of the Tōhoku Main Line between Hachinohe — Aomori was also transferred to Aomori Prefecture and Aoimori Railway.
This section serves as a major logistics artery connecting the Kantō region and Hokkaidō . During the management transfer, the local governments and new operators requested an increase in track usage fees paid by JR Freight, which operates as a Category-2 Railway Business Operator on this section. They argued that the section maintains double-tracked and electrified infrastructure primarily for freight operations, facilities considered excessive in scale for the level of passenger service, and thus demanded that JR Freight abandon the "avoidable cost" method and instead pay usage fees that also reflect the maintenance burden of these additional facilities.
After discussions among the relevant parties, it was decided that the Japan Railway Construction Public Corporation—the special corporation that built the Shinkansen section (later reorganized as the Japan Railway Construction, Transport and Technology Agency)—would use part of the track usage fees it receives from JR East for Shinkansen operations to subsidize JR Freight's track usage payments. This arrangement has since been applied to later Shinkansen projects as well, with its validity set to continue until JR Freight is fully privatized.
Until the opening of the Hokkaidō Shinkansen in 2016, the overnight limited express trains Hokutosei and Cassiopeia, which operated between Ueno — Sapporo, continued running as through services operated jointly with JR lines.
Although the Ōminato Line and Hachinohe Line became "isolated" lines without direct connections to JR East's other conventional line network, the rolling stock used on these lines continued to be shared through the operation of interconnected (through-running) trains, even after the management transfer.
In the past, these lines also served as transfer routes for rolling stock being sent to factories in Akita or Kōriyama for maintenance or overhaul. However, after the division of JR's lines, these transfer routes were broken up, forcing trains that previously could be moved entirely within the Tōhoku region to take long detours via the Greater Tokyo Area and other regions.

With the opening of the section between Takasaki — Nagano (the so-called Nagano Shinkansen) on October 1, 1997, part of the Shinetsu Main Line was reorganized as follows: the Takasaki — Yokokawa section remained under JR East's operation; the Yokokawa — Karuizawa section was abolished; and the Karuizawa — Shinonoi section was transferred to the newly established Shinano Railway, a third-sector railway company. This became the first case of heikō zairaisen separation accompanying the opening of a Shinkansen line. The Shinonoi — Nagano section continued to be operated by JR East, as it plays a vital role in the transport network, with many trains from the Shinonoi Line running through to Nagano.
When the Nagano — Kanazawa section opened on March 14, 2015, parts of the Shinetsu Main Line and Hokuriku Main Line were transferred as follows:
At the time of the Kanazawa — Tsuruga section opening on March 16, 2024, management of the heikō zairaisen Hokuriku Main Line was again transferred: the Kanazawa — Daishōji section in Ishikawa Prefecture was taken over by IR Ishikawa Railway, while the Daishōji — Tsuruga section in Fukui Prefecture was transferred to Hapi-Line Fukui.
As for the Tsuruga — Shin-Osaka section, the Japan Railway Construction, Transport and Technology Agency (JRTT) published a preparatory environmental considerations report in May 2019 under the Environmental Impact Assessment Act (環境影響評価法), presenting an outline of the proposed route. However, the treatment of the heikō zairaisen for this future section remains undecided.
With the opening of the section between Shin-Yatsushiro — Kagoshima-Chūō on March 13, 2004, management of the Kagoshima Main Line section between Yatsushiro — Sendai was transferred to the third-sector company Hisatsu Orange Railway. In this section, JR Freight continues to operate as a Category-2 Railway Business Operator (providing freight services on tracks owned by another company) and is also a shareholder in the new company, maintaining its freight operations.
Although electrification facilities were retained for freight train operations, this section—particularly the sparsely populated area near the Kumamoto–Kagoshima prefectural border—was converted to the use of light diesel multiple units (DMUs) to reduce passenger service operating costs. The overnight trains that had previously operated along this line were discontinued from entering the Hisatsu Orange Railway section; the Naha sleeper train, which used to run between Shin-Osaka — Nishi-Kagoshima Stations, had its service shortened to Kumamoto before being discontinued on March 15, 2008.
However, JR Kyūshū's cruise train Seven Stars in Kyūshū (operating since 2013) and the D&S train (excursion train) 36+3 (launched in 2020) both run through this section.
All other sections of the line remain under JR Kyūshū's direct management, as they are integral parts of the urban transport network and were therefore not separated.
For the Nagasaki Main Line section between Hizen-Yamaguchi — Isahaya, it was initially agreed that the railway would adopt a vertical separation model in which Saga Prefecture and Nagasaki Prefecture would own the railway infrastructure. Under this plan, JR Kyūshū would operate the section between Hizen-Yamaguchi — Hizen-Kashima, while a third-sector railway company jointly established by the two prefectures would manage operations between Hizen-Kashima — Isahaya.
However, due to opposition from some local municipalities along the line to the proposed management separation, the plan was later revised so that JR Kyūshū would continue to operate the entire section of the heikō zairaisen for 23 years following the opening of the Shinkansen.
That said, the vertical separation model itself remains in place, and the Saga–Nagasaki Railway Management Center (佐賀・長崎鉄道管理センター), jointly established by the two prefectures, owns the railway facilities. The section between Isahaya — Nagasaki remains under JR Kyūshū's direct management and is not separated.
Among these sections, the stretch between Hizen-Hama — Nagasaki has had its electrification facilities removed and is now operated with diesel multiple units (DMUs). This case represents the first instance of electrification facilities being dismantled on a heikō zairaisen.
Although the promotion of Shinkansen construction is often justified on the grounds of correcting regional disparities and stimulating local development, some experts argue that it has, in fact, accelerated the decline of rural areas.
The reasons cited include the following:
Seibi Shinkansen lines' maximum operating speed is 260 km/h. This is because the National Shinkansen Railway Development Act—the legal basis for the construction of Seibi Shinkansen—sets the design maximum speed at 260 km/h. At the time the law was enacted in 1972, this figure was chosen with enough margin to allow for future speed increases.
Subsequently, with technological advancements, operational speeds of 320 km/h and 300 km/h have been achieved on lines such as the Tōhoku Shinkansen (Utsunomiya — Morioka section) and the Sanyō Shinkansen. However, the maximum speed on Seibi Shinkansen lines still remains at 260 km/h. This is partly because many of these sections do not have sufficient demand to justify higher speeds. In addition, increasing the design maximum speed for newly constructed sections would raise construction costs—thereby increasing the financial burden on local governments along the route—which is generally viewed unfavorably. Furthermore, as noted earlier, completed Seibi Shinkansen infrastructure is owned by JRTT and used by JR companies through track access charges. If the operational maximum speed were raised above 260 km/h, these charges likely would increase, making JR companies generally reluctant to pursue higher speeds.
However, on October 6, 2020, JR East announced plans to raise the maximum operating speed on the Tohōku Shinkansen between Morioka — Shin-Aomori from 260 km/h to 320 km/h in the future. The goal is to begin operations at the higher speed around 2027, once noise-reduction and related construction works are completed. Also, in May 2019, JR Hokkaidō requested that JRTT carry out additional works to enable a maximum operating speed of 320 km/h on the Hokkaidō Shinkansen, which the section between Shin-Hakodate-Hokuto — Sapporo is under construction, with the additional construction costs to be borne by the company itself. While the Tokyo–Sapporo market is expected to face competition from airlines, operation at 320 km/h would bring the Shinkansen travel time down to 4 hours and 30 minutes, allowing it to achieve a certain level of competitiveness. Subsequently, in its medium-term management plan announced in March 2024, JR Hokkaidō set a medium-term goal of raising the maximum speed of the Hokkaidō Shinkansen further to 360 km/h.
{{cite journal}}: CS1 maint: multiple names: authors list (link)