Project West Wind

West Wind Wind Farm
CountryNew Zealand
LocationMākara, west of Wellington City
Coordinates41°16′35″S 174°39′37″E / 41.27639°S 174.66028°E / -41.27639; 174.66028
StatusOperational
Construction beganSeptember 2007 (2007-09)
Commission dateApril 2009 (2009-04)
Construction cost$440 million
OwnerMeridian
Wind farm
TypeOnshore
Hub height68 m (223 ft)
Rotor diameter82 m (269 ft)
Rated wind speed13–14 m/s (47–50 km/h; 29–31 mph)
Power generation
Units operational62
Make and modelSiemens: SWT-2.3-82 VS
Nameplate capacity142.6 MW
Capacity factor44.0%
Annual net output550 GWh
External links
CommonsRelated media on Commons

West Wind is a wind farm located at Terawhiti Station and Mākara, west of Wellington, New Zealand. It was the first wind farm for the capital city, and has a capacity of 143 MW. It is owned and operated by Meridian Energy.

History

An aerial view of the Project West Wind wind farm at Mākara.
Project West Wind wind farm

Capital Power first proposed a wind farm at Quartz Hill in the Mākara area in 1995, conducting feasibility studies before deciding the project was not viable. The project was subsequently purchased by the Electricity Corporation of New Zealand, who revived it in 1997. The proposal was opposed by Mākara residents, who formed the Makara Guardians to oppose it. The project was subsequently delayed by the Fourth National Government's plans to reform the electricity sector. ECNZ was subsequently split into three competing State-owned enterprises, and Meridian Energy inherited the project.

The project was revived by Meridian in 2005, with a proposal for a 70 turbine, 210MW wind farm on the same site. Dubbed "Project West Wind", the wind farm would be larger than all existing New Zealand windfarms combined. Resource consent was granted in December 2006 and immediately appealed to the Environment Court. The Environment Court affirmed the consent in May 2007, but reduced the wind farm to 66 turbines. Meridian subsequently reviewed its plans, reducing the number of turbines to 62 and reducing their height from 125m to 111m.

Construction began in September 2007, with the turbines shipped to Picton before being transported to a temporary wharf at Oteranga Bay by barge. It was officially opened in April 2009, when Prime Minister John Key turned on the first 15 turbines. Electricity from the farm is stepped-up to 110 kV and is injected into Transpower's national grid via hard tee connections into two of the three Central Park to Wilton circuits (both circuits of the Central Park - Wilton B Line).

Six turbines suffered premature bearing failures in 2011.

In September 2019 Meridian celebrated 10 years of generation with the Mākara and Wellington community at the recreation area.